Muller UK

For this new production facility Phoenix were asked to supply over 600 linear metres of aluminium bullnose and fascia sections on this project.   All in all there were over 50 different abutment joints, each one having to be individually marked and fabricated to show the continuous contours around the building.

 

The overall girth of each of the bullnoses was nearly 2000mm proving to be one of the most difficult challenges to date to not only produce but also maintain consistency.

Specially designed brackets were manufactured to overcome this problem and factory bonded butt straps were applied where necessary. On the same contract Phoenix manufactured over 6.5 kilometers of continuous louvre blades complete with all necessary supports.

Working closely with the client, special blade lengths were made to suit individual area cutting down on waste and saving the client money. Both single and double bank louvre systems were supplied in Corus HPS200 Scintilla.